• Reconstruction of Aktau - Manasha Road Section Lot 2

    Kazakhstan

    The turn-key project covers the construction of 50.8 km road section between km 422 and km 472.8 with the following work items:

    -Site survey and mapping topographical survey

    -Quarries and borrow areas

    -Earth works operations (1,024,979 m3)

    -Production of Aggregate with different fractions (522,517 ton) -Screening and crushing operations

    -Base Course Pavement (94,944 m3)

    -Cement of Sub-base (134,263 m3)

    -Bituminous hot pavement operations (131,257 m3)

    -Pipe and Box culvert (21 Pcs)

    -Road Furniture and other miscellaneous works