ClientMinistry of Investments and Development of the Republic of Kazakhstan
Project Completion DateFS+50 Months ( estimated date on 25th of June 2023)
Capacity
ContractorAlarko(33,4%), Leading + Makyol (33,3%) + SKEC(33,3%)

Description of the Project

The Design Build (Including ESIA submission) for Almaty Ring Road Project at a length of 66 km located about 20 to 25 km from centre of Almaty city and runs through three regions of Almaty Oblast: Karasay region in the west (27.5 km), Ili region in the north (19.26 km) and Talgar region in the east (19.24 km). Total Length Main road concrete pavement (66km) 1 A Category + Interchange Ramps – Bridge 21EA (1,370m) / Viaduct 19EA (2,446m) / IC 7EA / Toll 15EA.