Client | ALTEK A.S. (Power Plants Construction, Operation & Trading Company Inc.) |
Design | Temel – Su |
Capacity | 42.000.000.000 kWh/year |
Contractor | Alarko Contracting Group (Alsim) |
Description of the Project
The turn-key Project consisted of the procurement and execution of all civil, mechanical and electrical works of the hydroelectric power plant including 2 turbines with a total capacity of 9,35 MW and 2 generators with a total capacity of 11.000 kVA.