Client | ALTEK A.S. (Power Plants Construction, Operation & Trading Company Inc.) |
Design | DOLSAR |
Capacity | 47.200.000 kWh/year |
Contractor | Alarko Contracting Group (Alsim) |
Description of the Project
The turn-key Project consisted of the procurement and execution of all civil, mechanical and electrical works of the hydroelectric power plant including 2 turbines with a total capacity of 10,4 MW and 2 generators with a total capacity of 12.000 kVA.