Client | Taisei Corporation,Japan |
Project Completion Date: | 2005 |
Capacity | 300 MW ( Power Plant ) – 86.000 m³/day ( Desalination Plant ) |
Contractor | Alarko Contracting Group ( Alsim ) |
Description of the Project | The construction project consists of procurement and execution of all civil works of the Desalination and Power Plant and Water Intake Structure and construction works of the plant and utility buildings. Main quantities of the project are : Earthworks : 850.000 m³ Reinforced concrete : 50.000 m³ Sheet piling : 6.000 m² Asphalt roads : 45.000 m² |