Client | Boryspil International Airport State Enterprise (BSI) |
Project Completion Date | 2011 |
Capacity | 4,000,000 passengers / year |
Contractor | Dogus Insaat ve Tic A.S & Alsim Alarko Sanayi ve Tesisleri ve Ticaret A.S & YDA Insaat ve Sanayi Ticaret A.S. Joint Venture (DAY JV) |
Description of the Project
The turn-key project covers the engineering, design, procurement and construction of the Boryspil International Airport with the installation of all modern mechanical, electrical, electronic and air navigation systems. The project includes the construction of New Passenger Terminal Building, additional Apron – Taxiway and Access Roads. Terminal Building shall be installed with all electrical, mechanical and special security systems as well as hydrant fuel supply system, construction of external water and sewage lines. Apron Floodlighting System and Taxiway Edge and Centre Line Lighting System have been also included within the scope of the Works.